VALUATION JOINT BOARD - ROBERTSON CENTRE, PAISLEY

Local Authority building contractors in Scotland by Project Management & Construction Ltd

Originally scheduled to be a 26 week programme, PMCL reduced the programme down to 21 weeks and bettered even that by finishing in 19 weeks! The client VJB, who manage the Electoral Role for Renfrewshire, were delighted and the workmanship and co-operation received from PMCL, especially as this was a "live" site and the rest of the office remained functioning throughout the contract period.

The project comprised of the upgrading of existing heating ventilation and electrical installations, provision of tea bars, new suspended ceilings in certain areas and replacement of floor coverings and internal decoration. The final touch was the installation of purpose made replacement doors and ironmongery. Due to the nature of the work, some variations arose and these were also catered for within the reduced contract period.

Client Project Value Duration
Valuation Joint Board and Renfrewshire Council Refurbishment of the Robertson Centre in Paisley £560,000 19 Weeks

Return to Projects >

Contact PM&CL
Project Management & Construction welcomes enquires throughout Glasgow and Scotland. For more information and advice on your building/construction project, please call us on 0141 810 1214, or if after hours, fill in our Enquiry Form and we’ll get back to you.